#FMRDPUpdate | Earlier today, the Department of Agriculture (DA) – RFO XII, through the Regional Agricultural Engineering Division, in collaboration with the Department of Public Works and Highways (DPWH) – 1st District Engineering Office (DEO) of Sultan Kudarat, conducted a Joint Pre-Final Inspection for the Farm-to-Market Road (FMR) project titled “Concreting of Highway Junction to Purok Masagana-Purok Sikat- Purok Dela Cruz, Brgy. Bambad FMR, Brgy. Bambad, Isulan, Sultan Kudarat” funded under the 2024 DA-Regular Fund.
This activity aimed to identify incomplete works prior to the final inspection and to establish a punch list of items that were either unfinished or not constructed as per the approved standards.
The said inspection was a collaborative effort between the aforementioned agencies and partners from the provincial and municipal Local Government Units (LGUs). Moreover, the initiative sought to assess the physical status of ongoing FMR Projects in accordance with the approved plans and specifications.
Following the inspection, an exit conference was held with representatives from DPWH to present the project assessment and discuss the issues and concerns identified during the Pre-Final Inspection.